Drinking Water Revolving Loan
Fund |
- Source of submissions where new projects were added to the Project Priority List
- Projects submitted
- Total loan estimate for all new projects
- Average loan estimate per new project
- Estimated costs per project category
- Percent of new projects by category
Source of submissions where new projects were added to the Project Priority List
| Publicly owned community water systems | 23 |
| Privately owned community water systems | 0 |
| Noncommunity water systems | 3 |
Projects submitted
| Fiscal Year | Total Projects | New Projects | Project Revisions | Ineligible Projects | Reason Not Eligible |
|---|---|---|---|---|---|
| 2012 | 47 | 31 | 13 | 3 | 1 lacked DNR plan |
| 2011 | 194 | 118 | 71 | 5 | 2 for growth |
| 2010 | 324 | 283 | 11 | 30 | 17 for growth 2 lacked private water testing data 7 lacked DNR plan 1 not infrastructure improvement 2 not public water systems 1 not submitted by owner |
Go to > top.
Total loan estimate for all new projects
| FY 2012 | FY 2011 | FY 2010 |
|---|---|---|
| $55,993,144 | $103,208.944 | $352,569,491 |
Go to > top.
Average loan estimate per new project
| FY 2012 | FY 2011 | FY 2010 |
|---|---|---|
| $1,806,230 | $946,871 | $1,245,829 |
Go to > top.
Estimated costs per project category
| Category | Number of Projects | Total Estimated Cost of All |
Average Estimated Cost per New Project |
|---|---|---|---|
| Source | 3 | $1,330,900 | $443,633 |
| Treatment | 6 | $38,606,817 | $6,434,469 |
| Storage | 3 | $1,105,000 | $368,333 |
| Distribution | 17 | $14,802,727 | $870,749 |
| New System and Consolidation | 0 | $0 | $0 |
| Conservation | 2 | $147,700 | $73,850 |
| Other | 0 | $0 | $0 |
Go to > top.
Percent of new projects by category
| Source | Treatment | Storage | Distribution | New System and Consolidation |
Conservation | Other |
|---|---|---|---|---|---|---|
| 9.7% | 19.4% | 9.7% | 54.8% | 0% | 6.4% | 0% |
Go to > top.