Drinking Water Revolving Loan Fund Logo

Drinking Water Revolving Loan Fund
2013 Project Priority List Submission
and Comparison Data

Source of submissions where new projects were added to the Project Priority List

Publicly owned community water systems 47
Privately owned community water systems 0

Projects submitted

Fiscal Year Total Projects New Projects Project Revisions Ineligible Projects Reason Not Eligible
2013 69 53 14 2

1 extension to unserved area
1 project asked to be removed

2012 47 31 13 3

1 lacked DNR Plan
1 needs private wells sealed
1 project already started

2011 194 118 71 5 2 lacked private water testing data
1 not submitted by owner

Go to > top.

Total loan estimate for all new projects

FY 2013 FY 2012 FY 2011
$52,393,213 $55,993,144 $103,208,944

Go to > top.

Average loan estimate per new project

FY 2013 FY 2012 FY 2011
$988,551 $1,806,230 $946,871

Go to > top.

Estimated costs per project category

Category Number of Projects

Total Estimated Cost of All
New Projects

Average Estimated Cost per
New Project
Source 2 $138,800 $69,400
Treatment 12 $19,585,600 $1,632,133
Storage 8 $5,777,400 $722,175
Distribution 24 $23,522,203 $980,092
New System and Consolidation 0 $0 $0
Conservation 4 $572,010 $143,003
Other 3 $2,797,200 $932,400

Go to > top.

Percent of new projects by category

Source Treatment Storage Distribution New System and
Consolidation
Conservation Other
3.8% 22.6% 15.1% 45.3% 0% 7.5% 5.7%

Go to > top.

Updated Wednesday, December 05, 2012 at 01:30PM