MDH Homeland Security Exercise and Evaluation Program (HSEEP) Training Cards
PDF formatted for print: MDH HSEEP Training Cards (PDF: 53KB/8 pages)
To make the cards, print each page double sided. (Open the PDF, go to Print, click on “Properties,” then “two-sided printing” and “yes, flip over.”) Each card will show the step and relevant information. You can laminate and cut the cards if they will be used more than once.
On this page:
1. Concept and Objectives Meetings
2. Initial Planning Conference
3. Middle Planning Conference
4. MSEL Conference
5. Final Planning Conference
6. Controller and Evaluator Briefing
7. Player Briefing
8. Conduct Exercises
9. Player Hotwash
10. Controller and Evaluator Debriefing
11. After Action Report and Improvement Plan (AAR/IP)
12. After Action Conference
Card 13
Card 14
Card 15
1. Concept and Objectives Meetings
When:
- Tabletop exercise (TTX) – 4-5 months before exercise
- Functional exercise (FE) – 7-8 months before exercise
- Full-scale exercise (FSE) –12-13 months before exercise
Outcomes:
1. Purpose and goals of the Exercise
2. Type of exercise
3. Budget for the exercise
4. Timeframe and location
5. Participating jurisdictions, agencies, and organizations
6. Who should be represented on the exercise planning team
7. Date for the Initial Planning Conference
2. Initial Planning Conference
When:
- Tabletop exercise (TTX) -- 4 months before exercise
- Functional exercise (FE) -- 7 months before exercise
- Full-scale exercise (FSE) --12 months before exercise
Outcomes
- Scope of the exercise
- Exercise Name
- Purpose
- Type of exercise
- Participants—level of participation
- Date
- Location
- Goals and Objectives (must be associated with Target Capabilities)
- h. Exercise assumptions and artificialities (requirements and conditions)
- i. Scenario variables—time, location, hazard selection)
- 2. Identify Exercise Director, Control Lead, Evaluation Lead, and Logistics Lead
- 3. Begin documentation—OEP Exercise Notification Form (mirrors information that is submitted to the National Exercise Scheduler (NEXS) at the HSEEP site.
- 4. Assign responsibilities for Exercise Plan (EXPLAN)/(Situation Manual in a tabletop exercise), Controller and Evaluator Book (C/E Book)
3. Middle Planning Conference
When:
- FE—4 months before exercise
- FSE—6 months before exercise
Outcomes:
- Review documentation—EXPLAN, Draft of Controller and Evaluator Handbook with the Master Scenario Events List (MSEL)
- Possible walkthrough of exercise site/layout
- Develop the MSEL exercise timeline, associated scenario injects or determine if one or more MSEL conferences will be needed.
- Review Logistics needs for the exercise
- Assign additional responsibilities with date of completion
- Determine date and time for MSEL conference(s) and Final Planning Conference (FPC).
4. MSEL* Conference
When: 90 days before exercise
Outcomes
- Identify major and minor events that should occur during the exercise.
- Determine expected responses event by each player
- Determine if the conditions established will trigger the expected response, provide a secondary prompt through a message/data inject to be used if needed.
- Determine what responses need an informational inject to stimulate the expected response.
- Identify the method used to introduce each message/data inject.
- Organize major and minor events and messages chronologically; assigning a time for each event/message.
- Create the draft MSEL document
- Additional assignments and date to complete the MSEL
* Master Scenario Events List
5. Final Planning Conference
When:
- TTX – 45 days before exercise
- FE, FSE – 60 days before exercise
Outcomes:
- Review the entire exercise processes and procedures. No major changes should occur at the FPC.
- Resolve any open issues related to the exercise documents and materials.
- Review and verify the logistics needs of the exercise.
- Determine additional assignments and completion date.
- Conduct a final comprehensive review of all documents:
- the EXPLAN/ SITMAN
- C/E Book with the MSEL
- Player book
- Briefing materials (for player briefing and controller/evaluator training)
- Reference materials to be provided to players
6. Controller and Evaluator Briefing
When: 2 to 5 days before exercise
Outcomes:
- Review the C/E Book
- Identify all assignments and locations
- Provide badges/identification
- Walk through of exercise site if possible
- Q&A
7. Player Briefing
When: Immediately before exercise
Outcomes:
- Provide badging/identification
- Review the Player Book
- Review references
- Overview of exercise site
- Review Safety and Call-off procedures
8. Conduct Exercises
When: During the exercise
Controllers:
- Initiate the play and monitor players’ actions
- Monitor and record the injects and player expected actions
- Ensure participants’ safety
Players:
- Respond to the events and injects
Evaluators:
- Observe players’ actions
- Record significant decisions/actions/outcomes
- Help ensure participants’ safety of the by reporting to the controller
9. Player Hotwash
When: Immediately after the exercise (next day if exercise ends late or not all players present)
Outcomes:
- Participant feedback
- What went well and should be continued
- What did not go well and should be improved
- Recommendations on how to improve
- Recover badges/identification
- Recover reference materials
10. Controller and Evaluator Debriefing
When: Within a week after the exercise
Outcomes:
- Review the exercise and note changes from the MSEL
- Document controller and evaluator observations
- Recover badges/identification
11. After Action Report and Improvement Plan (AAR/IP)
When: Draft After Action Report and Improvement Plan (AAR/IP) within 3 to 5 weeks of the exercise
Outcomes:
- Content from
- exercise documents
- participant feedback forms
- Player hotwash notes
- Controller and Evaluator debriefing notes
- Identify the participants for the After Action Conference (AAC)
- Date and invitations sent out for After Action Conference
- Draft AAR/IP reviewed by exercise planning team
- Draft AAR/IP sent to participants of After Action Conference at least a week prior to the date.
12. After Action Conference
When: No later than 60 days after the exercise
Outcomes:
- Review the After Action Report
- Review, revise, accept or decline each recommendation in the Improvement Plan matrix
- For accepted recommendations, define the corrective actions
- Assign corrective actions and due dates
- Finalize the AAR/IP
Card 13
Side 1: Minnesota Department of Health Homeland Security Exercise and Evaluation Program (HSEEP) Training Cards
Side 2:
Acronym List: AAC
After Action Conference
AAR/IP
After Action Report and Improvement Plan
CAP
Corrective Actions Program of HSEEP Toolkit
C/E
Controller and evaluator book
C&O
Concept and Objectives meeting
DDS
Design and Development System of HSEEP Toolkit
EXPLAN
Exercise Plan
FE
Functional Exercise
FPC
Final Planning Conference
FSE
Full-scale Exercise
HSEEP
Homeland Security Exercise and Evaluation Program
PC
Initial Planning Conference
MPC
Middle Planning Conference
MSEL
Master Scenario Events List
NEXS
National Exercise Scheduler of HSEEP Toolkit
TTX
Tabletop exercise
Card 14
Side 1: Minnesota Department of Health Homeland Security Exercise and Evaluation Program (HSEEP) Training Cards
Side 2:
Sources
- Homeland Security Exercise and Evaluation Program Volume II. Exercise Planning and Conduct https://hseep.dhs.gov/pages/1001_HSEEP7.aspx
- Minnesota Department of Health, Office of Emergency Preparedness
- For more information, contact Elizabeth Tangwall at Elizabeth.tangwall@state.mn.us or call 651-201-5127
Card 15
Side 1: Minnesota Department of Health Homeland Security Exercise and Evaluation Program (HSEEP) Training Cards
Side 2:
Correct order of MDH Homeland Security Exercise and Evaluation Program (HSEEP) Training Cards
1. Concept and Objectives Meetings
2. Initial Planning Conference
3. Middle Planning Conference
4. MSEL Conference
5. Final Planning Conference
6. Controller and Evaluator Briefing
7. Player Briefing
8. Player Hotwash
9. Controller and Evaluator Debriefing
10. After Action Report and Improvement Plan (AAR/IP)
11. Conduct Exercises
12. After Action Conference